Microtunneling GRP Pipe Systems in the Emirates
The ground conditions were very poor and soil consisted of layered mudstone, gypsum and sandy-silt with a high ground water table. The total project was divided into several contracts, whereas the biggest part was realized by the local firm. This section consisted of approx. 24 km in a diameter range of DN 400 to 1800 and HOBAS received the order to supply half of the project. HOBAS CC-GRP Pipe Systems were installed with a special concrete surrounding. The reason for the reinforced pipe is the tunnel boring machine, which has a certain diameter. The size of the machine does not have to be changed when the diameter of the GRP Pipe varies. The main reason why HOBAS CC-GRP Pipe Systems were taken was the smooth and highly corrosion resistant inner liner.
More information about this application
PROJECT DETAILS
Project ID: [15547] | |
Country: | United Arab Emirates |
City: | Abu Dhabi |
Year: | 2001 |
Application: | Sewer |
Installation: | Microtunneling |
Technology: | Hobas |
Total Length: | 24000 m |
Nominal Diameter DN: | 400 | 1800 mm |
Nominal Pressure PN: | 1 bar |
Nominal Stiffness SN: | 10000 N/m2 |