Poland
Warsaw
2023-2024
Other Pipelines
2100 m
Find the Polish version below
In August 2022, construction began on a new tram route in Warsaw, connecting Mokotów with Wilanów. The 6.5-kilometer route leads from Puławska Street, through Goworka, Spacerowa, Belwederska and Sobieskiego to the terminal at the intersection of Rzeczypospolitej and Branickiego Avenues. It provides a faster and more comfortable way for residents of Wilanów to reach the city center in just 30 minutes. The project also focused on building a reliable and safe infrastructure.
As part of the construction, Amiblu GRP casing pipes were installed in 2023 to protect underground water supply and heating networks. Amiblu pipes offer key advantages such as low weight, resistance to stray currents, and no need for cathodic protection. Their exceptional technical properties allow them to withstand the pressure and loads caused by trams and cars, ensuring long-term durability and the reliability of the entire system. Amiblu’s expertise made them a trusted partner in providing a safe and robust solution for this critical infrastructure project.
W sierpniu 2022 r. rozpoczęto prace nad budową trasy tramwajowej, łączącej Mokotów z Wilanowem w Warszawie. 6,5-kilometrowa trasa prowadzi od ul. Puławskiej, przez Goworka, Spacerową, Belwederską i Sobieskiego aż do terminala u zbiegu al. Rzeczypospolitej i Branickiego. Dzięki tej inwestycji mieszkańcy Wilanowa mogą dotrzeć tramwajem do centrum miasta w ok. 30 minut. Budowa tramwaju do Wilanowa to także okazja do zapewnienia nowej, wygodnej i bezpiecznej infrastruktury.
Prace montażowe rur osłonowych GRP rozpoczęły się w 2023. Dzięki swym niezwykłym parametrom technicznych, posłużyły jako osłony dla podziemnych sieci wodociągowych, ciepłowniczych, chroniąc je przed obciążeniami wywoływanymi przez tramwaje i samochody, zapewniając trwałość i niezawodność systemu komunikacyjnego.
© Amiblu Holding GmbH, 2025